PNCUB Stage 2 Upgrade Onshore Civil & Offshore Systems

About the project

Pensar was engaged for the Port North Common User Berth (PNCUB) Upgrade Stage 2 works. The existing jetty and offshore platform required significant upgrade works that comprised civil construction, building, finishing, fire system reliability improvements, spill reduction risk improvements, electrical works, commissioning support, security system upgrades and suspended scaffolding over water works.

Location

Brisbane, Queensland

Client & Duration

Port of Brisbane Pty Ltd
May 2022 - Sep 2023

Project Scope

  • Relocation of fire hydrant booster assembly, installation of underground fire and potable water piping and underground electrical infrastructure
  • Fire-fighting system reliability improvements including various new systems and associated structural, mechanical, piping, electrical, instrumentation and controls works
  • Hardstand area preparation, erosion protection and construction of serviced operations building shell
  • Construction of a new ramp connecting the hardstand to the jetty
  • CCTV, PLC/SCADA and flood lighting installation.

Challenges

  • Working on an active fuel unloading platform meant the project team had to be adaptable due to evolving and changing conditions. For example, when an industrial tanker ship was being unloaded, strict security clearances often meant stand-down periods for workers
  • Scope changes to achieve Client’s project vision as works progressed
  • Demolition of the existing offshore building involved asbestos contaminated materials that required meticulous and staged loading of waste onto a skip barge

Achievements

  • Through constant and direct communication with the PBPL project management team and a successful delivery, our existing relationship with a valued client was strengthened
  • Successful delivery of a critical infrastructure project as per the specified timelines
  • Our team managed the site security and safety of passengers by clear site security and delineation for continued use of the active cruise terminal 
  • Appropriate construction site waste was re-purposed for road base and all unbound pavement works.

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.