Herston Quarter Redevelopment

About the project

The Herston Quarter Redevelopment involved a major intersection upgrade which required the design of new sewer and water infrastructure, identification of major optic fibre network carriers and the identification and potential relocation of the trunk network gas main.

Location

Herston, Qld

Client & Duration

Australian Unity
April 2019 - May 2020

Project Scope

  • Quality Level B investigation on all existing utilities throughout the project, to enable a preliminary design
  • The preliminary design enabled Pensar to target the existing utilities for potholing that were in conflict with the various design elements of the project
  • Set up and Management of Major traffic permits and controls

Challenges

  • Communication with local stakeholders was required due to the close proximity to the Royal Brisbane Hospital (RBH)
  • Access for all RBH staff was to be maintained throughout the project, which meant elaborate traffic management plans and additional traffic controllers to guide staff through the site safely
  • Emergency vehicle access was to be maintained through site at all times, requiring police control
  • Pensar discovered a large amount of undocumented utilities onsite
  • Due to the project's close proximity to the RBH and as per the client's requirements, our time on site was limited. Multiple crews were working in close proximity to get the project completed on time

Achievements

  • Undocumented utilities were located and potholed accurately to be incorporated into the design - this assisted the designers in their correspondence with the affected utility owners, to notify them of required protection or possible relocations
  • Pensar's utility reports assisted the designers in meeting their Utility Owner's Duty of Care
  • Completed the project within the tight time frame and on budget despite the additional staff, traffic control and permit requirements
  • Good communication between the Metro North, Herston Quarter and Pensar staff ensured the traffic control closures and requirements were well communicated and executed
  • No complaints from the client, due to effective communication

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.