One of our project team’s captured incredible timelapse footage of the base slab concrete pour for a 16ML treated water reservoir currently under construction for Clarence Valley Council. This milestone saw 698m3 of concrete expertly applied across 3000m2, marking a significant step forward in delivering this critical infrastructure.
As part of the full design and construction scope for the Rushforth Road WTP Reservoir Upgrade, Pensar is delivering a 16ML treated water reservoir, a 1.8ML chlorine contact tank, installation of DN900 GRP/MSCL pipelines, upgrades to the Tintenbar Pump Station and relocation of the water main to integrate with the new asset.
This project represents a major investment in water infrastructure for Clarence Valley Council, ensuring long-term reliability and capacity for the region. Check out the time lapse of the pour here.