Wetalla Aeration Upgrades D&C

About the project

The Wetalla WRF faced issues with a corroded aeration header and aging blowers that caused inefficiencies in the bioreactor. Pensar was engaged to install new positive displacement blowers and an above-ground header to resolve these problems. Additionally, the aerobic digesters required improved aeration, and Pensar was tasked with installing new duty/standby blowers and above-ground headers.

Location

Toowoomba, Queensland

Client & Duration

Toowoomba Regional Council
May 2023 - Jul 2024

Project Scope

  • Detailed design, supply, installation, and commissioning of the new Aerobic Digester 2 blower building
  • Refit of two existing buildings with new blowers and associated connecting pipework
  • Staged changeover of the existing blowers following the commissioning of the new blower building
  • Design and installation of two new motor control centres (MCCs) and 12 variable speed drives (VSDs).

Challenges

  • The primary challenge was ensuring the existing treatment plant remained fully operational during blower changeovers. This was managed through a carefully developed staging plan that maintained sufficient redundancy, allowing the new equipment to be commissioned without interrupting the process
  • Ensuring the treatment process was not disrupted during installation and commissioning was critical. Pensar collaborated closely with TRC, Rienmac, and pH Water to develop and execute a commissioning plan that integrated seamlessly with the ongoing operations. Expectations were managed through regular communication, aligning timelines, and ensuring all parties were informed and in agreement throughout the project.

Achievements

  • The construction was staged effectively to eliminate any shutdowns exceeding 4 hours, which ensured minimal impact on the treatment plant process
  • The project was successfully completed 2 months ahead of schedule, demonstrating effective planning and execution
  • All pipework was fabricated offsite without the need for on-site welding, facilitated by a detailed 3D laser scan and comprehensive 3D modeling, enhancing efficiency and safety
  • Zero safety or environment incidents. 

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.