UV Disinfection Program – Stage 2b D&C

About the project

Pensar was engaged by TasWater to complete the design, construction and commissioning of UV disinfection systems across five (5) water treatment plants located on the east and west coasts' of Tasmania.

Location

5 sites across Tasmania

Client & Duration

TasWater
November 2022 - December 2023

Challenges

  • Limited availability of existing asset information including up to date drawings, locations of assets and unknown services which made the integration of the new UV system into the existing treatment plants operations very challenging
  • Advance planning required to ensure there were no delays to the construction program due to works being completed across 5 locations on the east and west coasts of Tasmania, with some being remotely located with challenging access.

Achievements

  • Construction works were completed over a month ahead of schedule
  • Successful collaboration with client and internal stakeholders ensuring key project outcomes were captured in the design stage and built into the installation works
  • Complex water main connections were completed within very short shutdown windows (under 6 hours)
  • Zero issues were reported throughout the design, construction and commissioning phases.

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.