River Crossing Temporary Bypass Arrangement
About the project
The CTGM Bandon Grove Williams River Crossing Temporary Bypass Arrangement involves construction of new isolation and bypass arrangements on the Chichester Trunk Gravity Main, north and south of the Williams River crossing at Bandon Grove Reserve. The works will enable Hunter Water to isolate and temporarily bypass the existing dual DN900 pipelines while maintaining flow through the CTGM during future emergency repair or replacement works.
Location
Bandon Grove, NSW
Client & Duration
Hunter Water
Feb 2026 - Dec 2026
Challenges
- The CTGM is a critical water supply asset, conveying raw water from Chichester Dam to Dungog Water Treatment Plant and treated water to Dungog, Clarence Town, Paterson and the Coalfields region, while also
supplementing Newcastle and Lake Macquarie during high demand or network constraints - The existing Williams River crossing comprises dual DN900 pipelines that have operated for more than 100 years and are in poor condition, with current repairs requiring complete CTGM shutdown
- Shutdown works must be completed during the March to September lowdemand period, with Contractor works during CTGM shutdown limited to 24 hours to minimise customer impacts
- Cut-over and commissioning require detailed planning across isolation, dewatering, recharging, water quality, disinfection, communications, contingency measures and run sheets, while coordinating procurement,
access, utilities, community consultation, staging, testing and commissioning across Hunter Water land and private property easements.
Achievements
- Pensar is delivering enabling infrastructure that will allow Hunter Water to isolate and bypass the existing dual DN900 Williams River crossing while maintaining CTGM flow and continuity of supply to Dungog,
Clarence Town and Paterson - The completed bypass arrangements will provide capacity for a temporary PE100 bypass pipeline capable of conveying 30 ML/day through the CTGM
- The project will reduce future network risk by supporting emergency repairs and future replacement of the ageing DN900 river crossing pipelines
- Planning and delivery are structured around a tightly controlled shutdown methodology, including cut-over workshops, weekly coordination meetings and a Go / No Go meeting before cut-over works, strengthening Hunter Water’s ability to manage service continuity and regulatory risk.