Search...

Orford Water Treatment Plant Chlorine Upgrade

About the project

Electrical Infrastructure
Process Water Infrastructure

The Orford WTP Chlorine Upgrade involved the design and installation of a new 20ft containerised Chlorine Dosing Unit, providing a safer, more reliable and secure chlorination installation to replace the existing system.

The CDU comprises three chlorination trains, including two primary disinfection trains and a pre oxidation train. Approximately 70m of dual contained GF pipework was installed to transfer chlorine solution to the pre-oxidation dosing point.

Location

Orford, TAS

Client & Duration

TasWater
Aug 2025 - July 2026

Project Scope

  • Design and installation of the prefabricated 20ft Chlorine Dosing Unit
  • Separate chlorine cylinder and chlorination rooms within the CDU
  • Three chlorine dosing trains comprising two primary disinfection trains and one pre oxidation train
  • Chlorine dosing equipment, process pipework and associated controls
  • Approximately 70m of dual contained GF pipework to the pre oxidation dosing point
  • Process control equipment and PLC
  • Electrical installation, including wiring and distribution board within the CDU
  • Civil works required to install and connect the CDU to the existing plant
  • External works required to install, connect, operate and control the new CDU
  • Leak detection cells and exhaust ventilation systems within both CDU rooms
  • Integration of the new system with the existing water treatment plant.

Challenges

  • A key design challenge arose when it was identified that the pre oxidation dosing train was required to operate continuously and could not provide redundancy for the primary disinfection system as originally  intended
  • Pensar worked closely with TasWater’s Project Manager to develop and obtain approval for the required variation. Despite the resulting two-month delay to the design process, the construction program was maintained once the revised design was approved, allowing commissioning to commence as planned.

Achievements

  • Resolved a significant design and redundancy issue without compromising the required operational outcome
  • Adhered to the planned construction program following completion of the delayed design, enabling commissioning to commence as scheduled
  • Use of prefabricated structures provided construction efficiencies and reduced the amount of work required on site.

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.