Search...

Mt Thorley Reservoir Access Upgrade

About the project

The existing reservoir access at the Mt Thorley site was deemed unsafe for use, requiring a much needed upgrade.

Location

Mt Thorley, New South Wales

Client & Duration

Singleton Council
February 2021 - March 2021

Project Scope

  • A full detailed design of the new reservoir access structure and roof replacement, including 3D modelling and a CHAIR workshop
  • Demolition of the existing reservoir accessway including the roof sheeting, the handrail system around the top of the reservoir, and the access hatch on the reservoir roof
  • Completion of foundation works, including piling rig drilling through sandstone
  • Formwork, steel reinforcement and concrete works for the base access tower concrete slab
  • Construction of a 20m high access stairway at ground level
  • 130t crane for lifting and installation of stair access tower in one complete pre-fabricated section
  • Replacement of the reservoir handrail, roof sheeting and access hatch
  • Complete installation of new site

Challenges

  • Working at heights throughout the job identified the need to try and do as much of the works from the ground as possible
  • Pre planning with the fabrication contractor and collaboration between Pensar teams, allowed for a methodology ensuring minimal high risk work activities at all times
  • Implementation and continual management of high risk works with the replacement of the roof sheeting, access hatch and handrail on the reservoir roof
  • Completing the roof replacement works over a weekend to reduce and minimise the overall risks of interrupting the water supply to critical council customers

Achievements

  • During the shutdown works, compliance with water safety standards and Singleton Council’s critical requirements were maintained
  • Singleton Council allocated Pensar 24 hours to complete specific works under a plant shutdown. Pensar successfully completed these works in 12 hours
  • The original methodology was to build the stair tower from EWPs (Elevated Working Platforms), with a crane to lift and position the structural steel elements
    • A revised methodology allowed Pensar to build the structure on its side at ground level, and then lift the entirety of the structure into place with a 130t crane
    • The revised methodology provided a safer outcome by reducing working at heights risks, and reducing the overall works program for the client

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.