Harpers Hill Reservoir and Lochinvar Trunk Main Upgrade

About the project

The Harpers Hill Reservoir forms part of the Maitland/North Rothbury water supply system in New South Wales, Australia. The volume of the existing Harpers Hill Reservoir provides limited capacity to the overall system, with a high drawdown and fill frequency. Pensar designed and constructed a new 7 ML potable water reservoir and pipework system, including the extension of Harpers Hill Lane, and constructed a 2.4 km trunk main. The upgrade enables Hunter Water to strengthen its water security, supporting regional growth for the next 15 to 20 years.

Location

Harpers Hill, New South Wales

Client & Duration

Hunter Water
Jan 2024 - Feb 2026

Project Scope

  • Separable Portion 1 included the demolition of the existing reservoir and disposal of materials, the design and construction of a new 7ML potable water reservoir, pipework, control upgrades, access road upgrades, geotechnical investigations, testing and restoration.
  •  Separable Portion 2 included construction of 2.4km DN375 PVC trunk main from the Lochinvar Pump Station to the new reservoir along the New England Highway, including
    two under road bores.

Challenges

  • Management of multiple services within road reserve during design and construction phase
  • Mitigating the effects to the program and budget / resourcing during significant wet weather events during civil works
  • Due to exposure of significant artefacts found underground during works, subsequent heritage management was required
  • Health and safety management was required to mitigate the unexpected exposure of asbestos in ground during works
  • Careful planning and consideration were required to meet logistical challenges of concrete pour and quality of undertaking an 8-meter high in-situ wall, half circumference of reservoir, in one lift
  • Due to high winds on an exposed site and adverse weather impacts, Pensar needed to pivot and adapt the program to cater for unprecedent amounts of inclement weather
  • Management of unknown underground services.

Achievements

  • Targeted planning and procurement have allowed Pensar to accelerate program and deliver Separable Portion 2, six weeks ahead of date for practical completion on an original 35 week program
  • Early engagement of stakeholders and acceleration opportunities have been taken up in Separable Portion 1, and we are targeting a completion ahead of the original 71 week program
  • Positive subcontractor relations achieved through engagement and transparency, as well as responsive approaches to feedback both ensured and enhanced the quality of work and working environment.

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.