Great Keppel Island STP D&C

About the project

Electrical Infrastructure
Process Water Infrastructure

As part of the Queensland Government’s Great Keppel Island (Woppa) Concept Master Plan, Livingstone Shire Council engaged Pensar to design and construct a new membrane bioreactor sewage treatment plant, producing Class A+ effluent for 480 equivalent persons, along with supporting pump stations and irrigation infrastructure. The plant services the Great Keppel Island Hideaway Resort, Holiday Village, new visitor amenities and northern freehold allotments, with capacity for future growth – a foundational step in revitalising the island as a premier ecotourism destination.

Location

Great Keppel Island, QLD

Client & Duration

Livingstone Shire Council
Oct 2024 - Sep 2026

Project Scope

  • Site investigations (survey, geotechnical, environmental, services, influent quality)
  • Design and construction of a new 500EP MBR STP producing Class A+ effluent (10:2 N:P)
  • Installation of two duplex and 10 simplex sewer pump stations
  • Replacement of existing septic systems with new residential SPS units
  • Construction of a main SPS to transfer sewage to the new STP
  • Power reticulation from the island’s micro-grid to new assets
  • Expansion of the effluent irrigation system, including 25,000m² of new sprinkler irrigation
  • Commissioning, operator training, process optimisation, and performance validation.

Challenges

  • The project team engaged with a diverse range of stakeholders, including Traditional Owners, government bodies, accommodation providers and local residents, ensuring expectations were clearly understood, proactively managed and met throughout project delivery
  • The environmentally sensitive location, adjacent to the Great Barrier Reef Marine Park, required detailed planning, robust environmental controls and strict adherence to all applicable statutory and regulatory requirements
  • With limited reliable data available on the existing STP and influent quality, extensive field sampling and testing were undertaken to establish accurate baseline conditions and inform a robust process design
  • All materials and equipment were transported via private barge and unloaded within restricted hightide windows, requiring precise logistical planning, scheduling and coordination to maintain efficient project delivery.

Achievements

  • Design refinements delivered improved operational outcomes, including replacing the proposed drying beds with a dewatering screw press and optimising the irrigation pump station layout
  • With no on-island concrete supply available, Pensar managed all concrete batching and mix designs in-house to meet programme, quality and performance requirements
  • Efficient barge logistics planning reduced transport costs while ensuring materials and equipment arrived within restricted tidal windows to maintain programme continuity
  • Pensar developed a GIS platform integrating drone imagery, design and planning data, with field access via Google Maps. Terrestrial photogrammetry and drone technology further improved the accuracy and efficiency of site investigations.

Get the latest news

The future demands new thinking, new approaches, and new solutions. We’d love to share how we’re using the unique expertise and skills of our people to design a better world, and the work we’re doing to make it possible.

    Get in touch

    We challenge established thinking to deliver innovative solutions and work hand-in-hand with our clients to achieve their vision and build infrastructure for the future. Harness the power of our people on your next critical infrastructure project.