About the project
Pensar was engaged by Hunter Water to deliver the Edgeworth WWTW Diffusers Upgrade as Separable Portion 2 under the broader CS1429 Toronto WWTW Package 1 EAT Refurbishment contract. The works involved diffuser replacement and tank remediation across Bioreactors 1 and 2, supporting environmental licence compliance and improved aeration system performance.
Location
Edgeworth, NSW
Client & Duration
Hunter Water
Dec 2024 - Nov 2025
Project Scope
- Supply and replacement of diffuser body and membrane assemblies
- Installation of an additional 220 diffusers in each bioreactor, increasing installed diffuser capacity
- Draining of tanks and removal of accumulated solids, grit and rag
- Condition assessment of aeration pipework, diffuser systems, condensate lines and concrete
- Concrete repairs, joint replacement, leak testing and diffuser pattern testing.
Challenges
- Works were delivered within an operating wastewater treatment plant, requiring coordination with Hunter Water and Veolia to maintain treatment performance and
operational continuity - Shutdown planning was required to minimise the duration and number of planned interruptions, with no unplanned disruption to operational assets
- Accumulated grit and rag required tank draining, solids management, dewatering and disposal as putrescible waste in accordance with NSW EPA requirements
- Fugitive hydrogen sulphide from the inlet works and bioreactor splitter pit required temporary H2S monitoring and defined mitigation controls
- Confined space works, isolation interfaces and condition-based remediation required careful planning around live wastewater treatment assets.
Achievements
- Safely delivered diffuser replacement, tank cleaning and remediation works with minimal operational impact
- Maintained treatment performance and operational continuity throughout the bioreactor upgrades
- Replaced aging diffuser bodies and membranes, restoring aeration system reliability
- Increased installed diffuser capacity across Bioreactors 1 and 2 through activation of blank diffuser positions
- Completed concrete repairs, joint replacement and condition assessments to support future maintenance planning
- Modified aeration pipework to accommodate Hunter Water’s updated control philosophy and improve long-term functionality.