Brisbane International Cruise Terminal
About the project
The construction of Brisbane’s first dedicated mega-cruise ship terminal will allow Brisbane to accommodate cruise vessels of all sizes including the largest ocean-going cruise ships in the world.
Location
Port of Brisbane, Queensland
Client & Duration
Hindmarsh Construction
March 2019 — May 2020
Project Scope
- Electrical HV, LV and comms installation
- Construction of security CCTV infrastructure
- Construction of stormwater infrastructure including RCP, manholes & gullies and RCBC installation
- Gravel pavement construction and asphalt placement
- 1.5km of DN315 PE Potable watermain
- New 2 x DN150 UU water meter installations
- 230m of DN400 PE SEQ Reverse Osmosis recycled watermain installation
- UU DN315 live sewer rising main connection works
- Sewer gravity main and rising main installation
- Sewer pump station installation, construction and commissioning
- Sewer emergency storage tank installation and commissioning
Challenges
- The removal and replacement of Acid Sulphate Soils
- Working in a marine environment required strict environmental controls and works were to be staged around tidal conditions
- Working in a sand filled site presented ground condition challenges when it came to excavation and installation of services. The site was more susceptible to wind and rain erosion, slowing works
- Pensar was contracted to work with the client to finalise the design. This resulted in a full redesign and upgrade of the original design
- Pensar was to engage with the service providers to obtain approvals for the integration and connection to authority service mains
Achievements
- Pensar provided PoB a 100% finalised design, offering a practical solution and cost benefit to the client
- Pensar assisted PoB to introduce renewable energy onsite so that the completed terminal will be self-sufficient, for power supply
- Due to challenging site conditions and the need for a redesign, Pensar offered constructability advise throughout the project to accommodate the new design and ensure it’s fit for purpose