Braeside Tanks Replacement
About the project
Pensar was engaged to renew Stanmores 25-year asset service life through tank replacement, reducing rate of pipe scaling and corrosion by returning the aeration system to service, regaining operability of existing valving, enabling process flow to bypass tank so that tank maintenance does not stop supply.
Location
Nebo, Queensland
Client & Duration
Dec 2023 - Jul 2024
Project Scope
- Piping and valves
- Tank replacement
- Tank lining
- In tank screens
- Aerator blower and piping
- Flowmeter, civil and structural
- Electrical integration
- Instrumentation and controls
Challenges
- Successfully keeping the pump station online throughout the works duration via heavy staging and pre-planning
- Cutting into asbestos pipework with unknown conditions during strict 8-hour shutdowns
- Accurate logistics management and clear communication was undertaken to ensure our teams had the correct materials on site when required due to this project's rural location.
Achievements
- Positive and seamless stakeholder management
- All shutdowns adhered to the strict 8-hour shutdown window whilst successfully installing critical pipework on major sections of the pipeline
- Maintained existing hydraulic intent of pump station throughout works duration through effective staging.